Release timing
Stuart Donaldson
stu at asyn.com
Thu Jan 20 04:10:47 UTC 2005
Gervase Markham wrote:
> Stuart Donaldson wrote:
>
>> What about the idea of "Freezing" 4 months after a release, allowing
>> for an estimated 2 month stabilization time, give or take some
>> arbitrarily long time like Bugzilla just experienced.
>
>
> Replace the 4 with a 5, and the 2 with a 1 (as 1 month is how long
> Dave estimates stabilisation for 6-month cycles will take) and that's
> basically what I'm also suggesting :-)
>
I didn't get that out of the previous messages. We should be clear
about saying "Bugzilla will release approximately every 6 months or so,
with a feature freeze 5 months after release, and estimating 1 month for
stabilization.
Saying we release every 6 months, and more importantly putting dates to
it, implies that the clock does not get reset based on the release, but
is of a fixed period.
-Stuart-