Anybody working on expanded priorities?
Gregary Hendricks
ghendricks at novell.com
Wed Dec 19 21:57:30 UTC 2007
On Wed, 2007-12-19 at 11:01 -0800, Mark McWiggins wrote:
> Hello All,
>
> My company currently uses the terrible program ESP for defect tracking
> and I would like to move
> to Bugzilla. However, our company is set up to use a more fine-grained
> priority model with numbers
> not just P1 to P5 but more like 1 to 1000.
> Is anybody else already working on such a modification? If not I am
> interested in doing this. Please advise.
We simply created a custom field for this and then added a couple lines
of code to verify that he entry was a number between 1 and 1000. In all
it took maybe five minutes to implement.
Greg